A 2.2 MW grid tied system made comprised of nearly 9,000 Solon 220/16 modules that is set to be planted in only seven week on top of a Bucharest logistics center.
Berlin-based solar module producer Solon Energy is on the way to plant Bucharest’s biggest system in a seven week’s period.
Solon announced to finish installing the system of 8,000 if its 220/16 modules on top of the logistics center until the end of the month.
The 2.2 MW system is going to produce 2.8 MWh per year and about 15% of that generated energy will be spend by the firms in the building, and the rest of the green energy will go into the Romanian grid company, Transelectrica, fact that will guarantee green certificates for the company.
The logistics center is owned by Romanian PV installer SC Atwar & TH Services, a company that was founded by logistics company Elcyrom Realty & Development.